We have acquired an extensive knowledge of all aspects of boiler upgrades, as well as refurbishments on power stations throughout the UK. NGW have achieved the qualifications in Prince 2 Project Management.

NGW’s project management portfolio includes the following prestigious examples:

  • Project Engineer in charge of all casing repairs, replacement and boiler structure works at Fiddlers Ferry Power Station in 2001 to 2005, and 2007 to 2013 on 500 megawatt boilers.
  • Project Engineer for the SNCR project responsible for the installation of steel structures, supports, ductings, fans and new access galleries and platforms.  Forging a close working relationship with senior management of the power station in 2012/2013.
  • Project Engineer in 2010 on Connah's Quay Power Station overseeing the manufacture and installation of new boiler galleries and link access ways.
  • Site manager for P J Douglas Engineering in 2011 and 2012 overseeing the installation of new dynamic classifiers and the renewal of all 12” and 24” pulverised fuel pipework at Aberthaw Power Station in South Wales.
  • Site manager at Ironbridge Power Station overseeing the Installation of a BOFA System (Boosted over fire air) in 2007.
  • Site manager at Ironbridge Power Station overseeing the installation of new Lownox burners.
  • Site manager in 2005, 2006, 2007 for the skin casing replacement and boiler structure upgrades.
  • Site manager at Aberthaw Power Station in 2008 overseeing the refurbishment and upgrades of the Boiler Structure, burners, ductings, dampers and silencers.

Registered in England and Wales No. 06437238 | VAT UK GB 000 000 | © Copyright 2021 NGW Fabrications Limited

Terms & Conditions | Privacy

Designed and Developed by Omnisity

By continuing to use the site you agree to our privacy & cookies policy